Grid connection · England, United Kingdom

Battery storage 250 MW grid connection at Old Hill Farm Direct

Battery storage 250 MW grid connection at Old Hill Farm Direct is a planned grid connection in England, United Kingdom, with 250 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Old Hill Farm Direct)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toLackenby (via a grid supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toOld Hall Farm, Lackenby - BESS (matched by coordinates+technology+capacity, 0.37 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity250 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date10 May 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage132 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates54.5687, -1.1263Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit applied for: Old Hall Farm, Lackenby - BESS (planning authority Redcar and Cleveland, reference R/2025/0500/FFM)

How it compares

Battery storage 250 MW grid connection at Old Hill Farm Direct is the 225th-largest of 2,533 grid connections in England and the 308th-largest of 3,903 in the United Kingdom by capacity; its 250 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England225th of 2,533319,370 MW<0.1%
United Kingdom308th of 3,903446,745 MW<0.1%
All grid connections in our data1,434th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 240 power plants (80 operating, 746 MW), 111 substations and 4 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
LackenbyPower plant49.9 MWCancelled0.3 km
Old Hall Farm, Lackenby - BESSPower plant244 MWPlanned0.4 km
LackenbySubstation——0.4 km
Greystones Road, Grangetown - Battery Energy Storage SystemPower plant60 MWPermitted0.6 km
GrangetownSubstation——2.1 km
SpencerbeckSubstation——4.1 km
Data center, Redcar (OSM way 1055031579)Data center——6.6 km
Lumen Technologies data center, MiddlesbroughData center——7.1 km
Pulsant data center, EnglandData center——12 km

Grid operator and place

More from Northern Powergrid (Northeast) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom