Grid connection · England, United Kingdom

Hinkley Point C grid connection

Hinkley Point C grid connection is a planned grid connection in England, United Kingdom, with 3,340 MW of capacity, held by NNB Generation Company (HPC) Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connection site: Shurton 400kV Substation)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (Scoping)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
HolderNNB Generation Company (HPC) LimitedNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Attached toHinkley Point CNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Capacity3,340 MWNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyNuclearNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNational Grid Electricity Transmission plcNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date31 Mar 2029 (stage 1, cumulative 1,670 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Connection date31 Jul 2030 (stage 2, cumulative 3,340 MW)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Hinkley Point C grid connection is the 8th-largest of 2,533 grid connections in England and the 8th-largest of 3,903 in the United Kingdom by capacity; its 3,340 MW is 0.75% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England8th of 2,533319,370 MW1%
United Kingdom8th of 3,903446,745 MW0.75%
All grid connections in our data8th of 7,6161,281,251 MW0.26%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Stage 1 due to connect, 1,670 MW in total
  2. Stage 2 due to connect, 3,340 MW in total

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page