Data center · England, United Kingdom
Pulsant data center, England
Pulsant data center, England is a data center in England, United Kingdom, operated by Pulsant.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Operator | Pulsant | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
| Coordinates | 54.5514, -1.3152 | OpenStreetMap data centers · record · ODbL 1.0 · checked 24 Oct 2026 |
Research on this data center and its operator.Who owns it up to the parent company, its power supply, grid connection and planning status, and an introduction to the operator.
Request researchHow its operator compares
Pulsant operates 8 of the 191 data centers in the United Kingdom in our data with a named owner; 3 owners have more. Counts cover the data centers in our data that name an owner, holder or operator; an asset with several owners counts for each.
| Operator in United Kingdom | Rank | Data centers | Share |
|---|---|---|---|
| Equinix, Inc. | 1st | 13 | 6.8% |
| Digital Realty | 2nd | 10 | 5.2% |
| Virtus | 2nd | 10 | 5.2% |
| Pulsant | 4th | 8 | 4.2% |
| NTT Limited | 5th | 6 | 3.1% |
Nearby
Within 50 km of this data center: 256 power plants (83 operating, 786 MW), 240 grid connections (123 operating, 1,236 MW) and 129 substations, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Battery storage 50 MW grid connection at Preston Direct | Grid connection | 50 MW | Planned | 0.2 km |
| Battery storage 46.2 MW grid connection at Bowesfield Crescent BESS | Grid connection | 46.2 MW | Planned | 0.2 km |
| Bowesfield | Substation | — | — | 0.2 km |
| Bowesfield 33/11kV | Substation | — | — | 0.2 km |
| Bowesfield 66/11kV | Substation | — | — | 0.2 km |
| Bowesfield Ind Est | Power plant | 2.6 MW | Cancelled | 0.4 km |
| Bowesfield Flexible Energy Park | Power plant | 8 MW | Cancelled | 0.6 km |
| Lambs Hill | Power plant | 8 MW | Operating | 0.7 km |
| Growhow UK Ltd (Billingham) grid connection | Grid connection | 21.9 MW | Operating | 2.4 km |
Operator and place
More from Pulsant
- Pulsant South Londondata center
- Edinburgh SC-3data center
- Pulsant Edinburgh South Gyle SC-1data center
- Pulsant Milton Keynes SE-1data center
- Pulsant Maidenheaddata center
- Edinburgh SC-2data center
- Pulsant Reading Eastdata center
Other data centers in England
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.