Grid connection · England, United Kingdom

Solar 22.5 MW grid connection at Turnstall Solar Farm

Solar 22.5 MW grid connection at Turnstall Solar Farm is a planned grid connection in England, United Kingdom, with 22.5 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Turnstall Solar Farm)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toLeeming Bar/Skeeby (via a bulk supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toTunstall & East Appleton Solar Farm - Solar Farm (matched by coordinates+technology+capacity, 0.12 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity22.5 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date5 Apr 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage33 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates54.3585, -1.6358Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit applied for: Tunstall & East Appleton Solar Farm - Solar Farm (planning authority North Yorkshire, reference ZD25/00369/FULL)

How it compares

Solar 22.5 MW grid connection at Turnstall Solar Farm is the 971st-largest of 2,533 grid connections in England and the 1,564th-largest of 3,903 in the United Kingdom by capacity; its 22.5 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England971st of 2,533319,370 MW<0.1%
United Kingdom1,564th of 3,903446,745 MW<0.1%
All grid connections in our data5,151st of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 214 power plants (66 operating, 709 MW), 98 substations and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Tunstall & East Appleton Solar Farm - Solar FarmPower plant23.5 MWPlanned0.1 km
Land East of Appleton FarmPower plant5 MWOperating0.1 km
Arbour HillPower plant1 MWCancelled3.5 km
Leeming Bar/SkeebySubstation——6.1 km
Catterick CampSubstation——6.3 km
Richmond T1Substation——8.0 km
Pulsant data center, EnglandData center——30 km
Lumen Technologies data center, MiddlesbroughData center——36 km
DXC Wynyard Data CenterData center——37 km

Grid operator and place

More from Northern Powergrid (Northeast) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom