Grid connection · Scotland, United Kingdom

Strichen Solar Farm grid connection

Strichen Solar Farm grid connection is a planned grid connection in Scotland, United Kingdom, with 5 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSTRICHEN SOLAR FARM grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Strichen Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toStrichen Solar Project, Clayfords Farm - Solar Panels (matched by shared name+coordinates+technology+capacity, 1.69 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toStrichen Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity5 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date2 Oct 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.5830, -2.0592SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Strichen Solar Farm grid connection is the 809th-largest of 1,192 grid connections in Scotland and the 2,582nd-largest of 3,903 in the United Kingdom by capacity; its 5 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland809th of 1,19288,894 MW<0.1%
United Kingdom2,582nd of 3,903446,745 MW<0.1%
All grid connections in our data6,237th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 176 power plants (55 operating, 422 MW) and 59 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Strichen GSPSubstation——0.7 km
Strichen PrimarySubstation——0.8 km
Electricity Sub Station, Strichen - Battery Storage FacilityPower plant50 MWPermitted0.9 km
Strichen NorthPower plant25 MWCancelled1.5 km
Strichen Solar Project, Clayfords Farm - Solar PanelsPower plant6 MWPermitted1.7 km
Mintlaw PrimarySubstation——7.5 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page