Power plant · Aberdeenshire, Scotland, United Kingdom

Electricity Sub Station, Strichen - Battery Storage Facility

Electricity Sub Station, Strichen - Battery Storage Facility is a permitted power plant in Aberdeenshire, Scotland, United Kingdom, with 50 MW of capacity, operated by Intelligent Land Investments Group.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAberdeenshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressAdj Electricity Sub Station Strichen, AB43 6RHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date1 Mar 2022 (permit APP/2021/2556, Town and Country Planning Act, issued by Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date19 Nov 2021 (reference APP/2021/2556, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date1 Mar 2022 (granted, reference APP/2021/2556, planning authority Aberdeenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorIntelligent Land Investments GroupDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity50 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates57.5908, -2.0617DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Electricity Sub Station, Strichen - Battery Storage Facility is the 285th-largest of 872 power plants planned, permitted or under construction in Scotland and the 755th-largest of 3,222 in the United Kingdom by capacity; its 50 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
Scotland285th of 87299,272 MW<0.1%
United Kingdom755th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,832nd of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 104 grid connections (49 operating, 269 MW), 56 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Strichen GSPSubstation——0.7 km
Strichen PrimarySubstation——0.7 km
Clayfords Energy Storage grid connectionGrid connection49.9 MWPlanned0.9 km
Strichen Solar Farm grid connectionGrid connection5 MWPlanned0.9 km
Redbog Windfarm grid connectionGrid connection1.52 MWOperating2.4 km
New Pitsligo PrimarySubstation——7.9 km
BrightsolidData center——49 km

Operator and place

Grid connections attached to this power plant

More from Intelligent Land Investments Group

Other power plants in Scotland

All 2093 power plants in Scotland, United Kingdom