Wester Covesea Solar, Wind and Storage grid connection is a planned grid connection in Scotland, United Kingdom, with 180 MW of capacity, held by BSR Applications Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceWESTER COVESEA SOLAR, WIND AND STORAGE grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Elgin Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderBSR Applications LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toElgin Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity180 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date16 Dec 2024SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Jun 2032 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.7098, -3.3810SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Wester Covesea Solar, Wind and Storage grid connection is the 51st-largest of 1,192 grid connections in Scotland and the 332nd-largest of 3,903 in the United Kingdom by capacity; its 180 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland51st of 1,19288,894 MW0.2%
United Kingdom332nd of 3,903446,745 MW<0.1%
All grid connections in our data2,239th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 109 power plants (32 operating, 3,105 MW) and 46 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
RAF Lossiemouth - Solar PanelsPower plant5.04 MWPlanned4.5 km
Loanhead Farm - Battery Energy Storage SystemPower plant49.9 MWPlanned4.8 km
Burghead PrimarySubstation——5.2 km
Lossiemouth PrimarySubstation——5.4 km
Bishopmill - Battery Energy StoragePower plant30 MWPermitted6.1 km
Elgin PrimarySubstation——6.1 km

Holder, grid operator and place

More from BSR Applications Limited

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page