Grid connection · Scotland, United Kingdom

Seggiecrook Farm BESS and Solar grid connection

Seggiecrook Farm BESS and Solar grid connection is a planned grid connection in Scotland, United Kingdom, with 126 MW of capacity, held by Greentech Projects Holding UK Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSEGGIECROOK FARM BESS AND SOLAR grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Keith Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderGreentech Projects Holding UK LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toKeith Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity126 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date3 Feb 2025SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2033 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.5561, -2.7986SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Seggiecrook Farm BESS and Solar grid connection is the 54th-largest of 1,192 grid connections in Scotland and the 361st-largest of 3,903 in the United Kingdom by capacity; its 126 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland54th of 1,19288,894 MW0.14%
United Kingdom361st of 3,903446,745 MW<0.1%
All grid connections in our data2,731st of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 205 power plants (65 operating, 1,762 MW) and 54 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Limehillocks PrimarySubstation——1.4 km
Myreton CrossroadsPower plant1.6 MWOperating5.5 km
Netherton Of Windyhills (extension)Power plant2.3 MWCancelled5.7 km
Netherton of WindyhillsPower plant4.6 MWOperating6.3 km
Keith 2 GSPSubstation——8.5 km
Keith 1 GSPSubstation——8.5 km

Holder, grid operator and place

More from Greentech Projects Holding UK Limited

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom