Grid connection · Scotland, United Kingdom

Kirkton PV + ESS grid connection

Kirkton PV + ESS grid connection is a planned grid connection in Scotland, United Kingdom, with 43.8 MW of capacity, held by DNO Consulting Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceKIRKTON PV + ESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connection site: PETERHEAD GRANGE 33KV)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderDNO Consulting LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toPeterhead Grange Primary (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toFraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facility (method: shared name+coordinates+technology+capacity, distance km: 1.61)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity43.8 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date16 Dec 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date1 Oct 2026 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.5487, -1.8269SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Kirkton PV + ESS grid connection is the 334th-largest of 1,192 grid connections in Scotland and the 1,105th-largest of 3,903 in the United Kingdom by capacity; its 43.8 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland334th of 1,19288,894 MW<0.1%
United Kingdom1,105th of 3,903446,745 MW<0.1%
All grid connections in our data4,239th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 157 power plants (48 operating, 370 MW) and 53 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Bruxiehall FarmPower plant2 MWUnder construction1.5 km
Salamander Offshore Wind Farm - Battery Storage and Onshore ConnectionPower plant180 MWPermitted1.6 km
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage FacilityPower plant50 MWPermitted1.6 km
St Fergus GSPSubstation——3.4 km
Peterhead Grange GSPSubstation——4.6 km
Peterhead Grange PrimarySubstation——4.6 km

Holder, grid operator and place

More from DNO Consulting Ltd

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom