Grid connection · England, United Kingdom
Parley Court Farm grid connection
Parley Court Farm grid connection is a planned grid connection in England, United Kingdom, with 50 MW of capacity, held by DNO Consulting Ltd.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | PARLEY COURT FARM grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Redhill) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | DNO Consulting Ltd | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Parley Court - Solar Farm (matched by name+coordinates+technology, 0.59 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | Redhill Primary (via a primary substation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 50 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Southern Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 24 Jun 2021 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 6 Dec 2036 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 50.7749, -1.8596 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its holder? Ask us.
How it compares
Parley Court Farm grid connection is the 538th-largest of 2,533 grid connections in England and the 804th-largest of 3,903 in the United Kingdom by capacity; its 50 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 538th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 804th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 3,801st of 7,616 | 1,281,251 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 250 power plants (113 operating, 955 MW), 153 substations and 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Hale Farm | Power plant | 8 MW | Operating | 0.4 km |
| Parley Court - Solar Farm | Power plant | 35 MW | Permitted | 0.6 km |
| Woodtown Farm | Power plant | 3.8 MW | Operating | 0.7 km |
| Redhill BSP | Substation | — | — | 1.8 km |
| Redhill Primary | Substation | — | — | 1.9 km |
| Winton Primary | Substation | — | — | 3.5 km |
| Data Vault - Bournemouth BCP01 | Data center | — | — | 6.0 km |
| Sky Chilworth | Data center | — | — | 37 km |
| SCC | Data center | — | — | 44 km |
Holder, grid operator and place
More from DNO Consulting Ltd
- Row Hill Farm grid connection99.9 MW
- Kirkton PV + ESS grid connection43.8 MW
- Northacre Resource Recovery Plant grid connection35.5 MW
- Pipplepen Farm Solar PV grid connection32.6 MW
- Cordon Farm grid connection30 MW
- 10MW Cruxton Farm PV grid connection20 MW
- Motcombe Solar grid connection12 MW
- 8.55MW Battery grid connection8.55 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. Checked 2026-10-24. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.