Grid connection · England, United Kingdom
Wickham PV Plant grid connection
Wickham PV Plant grid connection is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, held by Conrad Energy Developments II Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | WICKHAM PV PLANT grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Botley Wood) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Conrad Energy Developments II Limited | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Titchfield Lane, Wickham - Solar Panels (matched by shared name+coordinates+technology+capacity+company, 1.37 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | Botley Wood BSP (via a primary substation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Southern Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 4 Mar 2022 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 15 Nov 2037 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 50.8923, -1.2106 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection and the records linked to it from official notices, registers and owners' press releases, newest first. All recent changes.
- Permit granted: Titchfield Lane, Wickham - Solar Panels (planning authority Winchester, reference 24/02804/FUL)
- Permit applied for: Titchfield Lane, Wickham - Solar Panels (planning authority Winchester, reference 24/02804/FUL)
How it compares
Wickham PV Plant grid connection is the 595th-largest of 2,533 grid connections in England and the 902nd-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 595th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 902nd of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,268th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 266 power plants (120 operating, 2,209 MW), 181 substations, 7 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Fontley House Farm | Power plant | 10 MW | Cancelled | 0.5 km |
| Ash Farm, Titchfield Lane - Battery Storage | Power plant | 15 MW | Permitted | 0.7 km |
| Titchfield Lane | Power plant | 49 MW | Under construction | 1.0 km |
| Botley Wood BSP | Substation | — | — | 1.8 km |
| Botley Wood GSP | Substation | — | — | 1.8 km |
| Regit4u | Data center | — | — | 3.2 km |
| Whitely Primary | Substation | — | — | 3.2 km |
| Serverhouse | Data center | — | — | 3.7 km |
| Astrohouse | Data center | — | — | 3.7 km |
Holder, grid operator and place
More from Conrad Energy Developments II Limited
- Fawley Battery Energy Storage Plant grid connection99 MW
- Truncheaunts Farm grid connection49.9 MW
- North Leylodge grid connection49.9 MW
- Coldstream Solar PV Plant (Elwartlaw Farm) grid connection40.6 MW
- 25.3MW Battery grid connection25.3 MW
- Pets Choice Ltd grid connection24.2 MW
- Dunbar Solar PV Scheme grid connection20 MW
- Yeovil Leonardo Power Generation Plant grid connection9 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.