Grid connection · England, United Kingdom

25.3MW Battery grid connection

25.3MW Battery grid connection is a planned grid connection in England, United Kingdom, with 25.3 MW of capacity, held by Conrad Energy (Developments) II Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the source25.3MW BATTERY grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connection site: NORRINGTON)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderConrad Energy (Developments) II LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toNorrington BSP (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity25.3 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date6 May 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date15 Nov 2037 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.3848, -2.1681SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

25.3MW Battery grid connection is the 951st-largest of 2,678 grid connections in England and the 1,644th-largest of 4,493 in the United Kingdom by capacity; its 25.3 MW is <0.1% of the 459,551 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England951st of 2,678322,469 MW<0.1%
United Kingdom1,644th of 4,493459,551 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 96 substations, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Norrington BSPSubstation——0.2 km
Melksham GSPSubstation——1.5 km
Melksham Town PrimarySubstation——2.0 km

Holder, grid operator and place

More from Conrad Energy (Developments) II Limited

Other grid connections in England

All 3977 grid connections in England, United Kingdom