Waste 10 MW grid connection at Billingham Energy Waste

Waste 10 MW grid connection at Billingham Energy Waste is a planned grid connection in England, United Kingdom, with 10 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Billingham Energy Waste)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toBillingham Chemical Works (matched by coordinates+technology+capacity, 0.43 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toNorth Tees (via a bulk supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity10 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWasteNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date8 Nov 2024Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage66 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates54.5887, -1.2742Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Commissioned: Billingham Chemical Works
  2. Permit granted: Billingham Chemical Works (planning authority Stockton-on-Tees, reference 10/1464/EIS)
  3. Permit applied for: Billingham Chemical Works (planning authority Stockton-on-Tees, reference 10/1464/EIS)

How it compares

Waste 10 MW grid connection at Billingham Energy Waste is the 1,332nd-largest of 2,533 grid connections in England and the 2,105th-largest of 3,903 in the United Kingdom by capacity; its 10 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,332nd of 2,533319,370 MW<0.1%
United Kingdom2,105th of 3,903446,745 MW<0.1%
All grid connections in our data5,969th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 266 power plants (89 operating, 2,237 MW), 145 substations and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Billingham Chemical WorksPower plant12 MWOperating0.4 km
Norton BottomsPower plant5 MWCancelled0.8 km
North TeesSubstation——0.9 km
North Tees T1 T2Substation——0.9 km
North Tees T3 T4Substation——0.9 km
Billingham Biomass Power StationPower plant49.8 MWCancelled1.0 km
Lumen Technologies data center, MiddlesbroughData center——2.8 km
Pulsant data center, EnglandData center——4.9 km
DXC Wynyard Data CenterData center——5.5 km

Grid operator and place

More from Northern Powergrid (Northeast) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page