Grid connection · Scotland, United Kingdom

Altens 10MW PV + Electolyser grid connection

Altens 10MW PV + Electolyser grid connection is a planned grid connection in Scotland, United Kingdom, with 10 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceALTENS 10MW PV + ELECTOLYSER grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Redmoss Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toRedmoss Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toAltens Incinerator (matched by shared name+coordinates+technology+capacity, 1.1 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity10 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyADVANCED FUEL GASIFICATION OR PYROLYSISSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date23 Jun 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Jul 2026 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.1154, -2.0786SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit refused: Altens Incinerator (planning authority Aberdeen City, reference A11844)
  2. Permit applied for: Altens Incinerator (planning authority Aberdeen City, reference A11844)

How it compares

Altens 10MW PV + Electolyser grid connection is the 680th-largest of 1,192 grid connections in Scotland and the 2,105th-largest of 3,903 in the United Kingdom by capacity; its 10 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland680th of 1,19288,894 MW<0.1%
United Kingdom2,105th of 3,903446,745 MW<0.1%
All grid connections in our data5,969th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Nearby

Within 50 km of this grid connection: 165 power plants (48 operating, 544 MW), 70 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Craigshaw Drive - Battery Storage Facility & Electric Vehicle Charging HubPower plant20 MWPermitted1.0 km
Kincorth PrimarySubstation——1.0 km
Altens IncineratorPower plant12 MWCancelled1.1 km
Redmoss GSPSubstation——1.1 km
Redmoss PrimarySubstation——1.1 km
Ness Energy ProjectPower plant11.1 MWOperating1.5 km
BrightsolidData center——6.4 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page