Solar 5 MW grid connection at Thirsk

Solar 5 MW grid connection at Thirsk is a grid connection in England, United Kingdom, with 5 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Thirsk)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (connected)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toThirsk (via a primary substation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity5 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date29 Jul 2016Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Connection date1 Mar 2017Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates54.2339, -1.4123Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Solar 5 MW grid connection at Thirsk is the 1,667th-largest of 2,533 grid connections in England and the 2,582nd-largest of 3,903 in the United Kingdom by capacity; its 5 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,667th of 2,533319,370 MW<0.1%
United Kingdom2,582nd of 3,903446,745 MW<0.1%
All grid connections in our data6,544th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 201 power plants (60 operating, 645 MW), 151 substations, 5 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Land North of Sandhutton LanePower plant5 MWOperating1.2 km
ThirskSubstation——1.6 km
Barugh FarmPower plant5 MWOperating8.3 km
Sessay Bridge/SowerbySubstation——9.0 km
Cold Harbour FarmPower plant5 MWOperating9.6 km
RomanbySubstation——11 km
VocaLinkData center——30 km
Pulsant data center, EnglandData center——36 km
Yorkshire GREENTransmission line—Permitted38 km