Grid connection · England, United Kingdom

Solar 4 MW grid connection at Ellifoot Lane

Solar 4 MW grid connection at Ellifoot Lane is a planned grid connection in England, United Kingdom, with 4 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Ellifoot Lane)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toEllifoot Lane (via a primary substation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity4 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date12 Oct 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7623, -0.7039Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Solar 4 MW grid connection at Ellifoot Lane is the 1,830th-largest of 2,533 grid connections in England and the 2,840th-largest of 3,903 in the United Kingdom by capacity; its 4 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,830th of 2,533319,370 MW<0.1%
United Kingdom2,840th of 3,903446,745 MW<0.1%
All grid connections in our data6,514th of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 461 power plants (112 operating, 4,203 MW), 189 substations, 3 transmission lines, 3 data centers and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Yorkshire Grown Produce, Main Road - Biomass BoilerPower plant4 MWPermitted0.1 km
Newport 1Substation——0.6 km
Newport 2Substation——0.6 km
Yorkshire Grown Produce, Main Road - Solar PanelsPower plant1.5 MWPermitted1.3 km
Newton Farm, Tongue Lane - Solar Farm & Battery StoragePower plant1.5 MWPermitted1.8 km
Holme Upon Spalding MoorSubstation——7.5 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled19 km
North Humber to High MarnhamTransmission line—Planned35 km
ThalesData center——39 km