Power plant · East Riding of Yorkshire, England, United Kingdom

Yorkshire Grown Produce, Main Road - Solar Panels

Yorkshire Grown Produce, Main Road - Solar Panels is a permitted power plant in East Riding of Yorkshire, England, United Kingdom, with 1.5 MW of capacity, operated by Yorkshire Grown Produce Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEast Riding of Yorkshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressYorkshire Grown Produce Limited, Main Road, Brough, HU15 2RHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Feb 2024 (permit 24/00009/PVNOT, Town and Country Planning Act, issued by East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date2 Jan 2024 (ref. 24/00009/PVNOT, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Feb 2024 (granted, ref. 24/00009/PVNOT, East Riding of Yorkshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorYorkshire Grown Produce LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.7668, -0.6858DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Yorkshire Grown Produce, Main Road - Solar Panels is the 1,935th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,924th-largest of 3,222 in the United Kingdom by capacity; its 1.5 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,935th of 2,174186,088 MW<0.1%
United Kingdom2,924th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data6,143rd of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 407 grid connections (192 operating, 2,743 MW), 186 substations, 3 transmission lines and 1 CO2 emitter, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Newport 1Substation——0.7 km
Newport 2Substation——0.7 km
Newport Building grid connectionGrid connection1.1 MWPlanned1.2 km
Newport Building grid connectionGrid connection1.4 MWPlanned1.2 km
Solar 4 MW grid connection at Ellifoot LaneGrid connection4 MWPlanned1.3 km
Holme Upon Spalding MoorSubstation——8.2 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled18 km
North Humber to High MarnhamTransmission line—Planned36 km
Aldbrough Hydrogen StorageCO2 emitter—Planned40 km

Operator and place

More from Yorkshire Grown Produce Limited

Other power plants in England

All 5809 power plants in England, United Kingdom