Grid connection · England, United Kingdom
Gowy Landfill 5 grid connection
Gowy Landfill 5 grid connection is a planned grid connection in England, United Kingdom, with 8 MW of capacity, held by Infinis.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connection site: CHESTER MAIN GT4 / CRANE BANK GT1 / GUILDEN SUTTON GT1 / SALTNEY G2A) | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (Accepted to Connect) | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Infinis | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 8 MW | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | SP Manweb | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 1 Dec 2030 (target energisation) | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its holder? Ask us.
How it compares
Gowy Landfill 5 grid connection is the 1,436th-largest of 2,533 grid connections in England and the 2,274th-largest of 3,903 in the United Kingdom by capacity; its 8 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,436th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 2,274th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 5,901st of 7,616 | 1,281,251 MW | <0.1% |
Holder, grid operator and place
More from Infinis
- Sutton Courtenay Landfill Site grid connection14.3 MW
- Sutton Courtenay grid connection12.5 MW
- Waste 2.375 MW grid connection at CALNE2.38 MW
- Landfill gas 1.9 MW grid connection at Chichester1.9 MW
- Pancross & Oaklands Solar Farm50 MW · under construction
- Pancross & Oaklands Solar Farm50 MW · under construction
- A'Chruach (Phase 1)48.3 MW
- Bishampton Solar Farm30 MW · under construction
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- CAISO queue report. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, No restriction on the posted data.
- PJM New Services Queue. PJM New Services Queue, No restriction on the posted data.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.