Grid connection · England, United Kingdom
Solar 17.3 MW grid connection at Marston Road Grid 33kV
Solar 17.3 MW grid connection at Marston Road Grid 33kV is a planned grid connection in England, United Kingdom, with 17.3 MW of capacity, held by Infinis Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connects at Marston Road Grid 33kV) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Status | Planned (accepted to connect) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Holder | Infinis Limited | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Capacity | 17.3 MW | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Solar | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Queue date | 8 Dec 2022 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Connection date | 31 Oct 2031 (target energisation) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 33 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 52.0697, -0.5234 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
How it compares
Solar 17.3 MW grid connection at Marston Road Grid 33kV is the 1,506th-largest of 3,539 grid connections in England and the 2,149th-largest of 4,870 in the United Kingdom by capacity; its 17.3 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,506th of 3,539 | 341,715 MW | <0.1% |
| United Kingdom | 2,149th of 4,870 | 467,981 MW | <0.1% |
| All grid connections in our data | 5,694th of 8,618 | 1,355,288 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 457 power plants (160 operating, 2,304 MW), 163 substations and 17 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Rookery South | Power plant | 65 MW | Operating | 0.7 km |
| Marston Vale Country Park Wind Turbine | Power plant | 1.5 MW | Operating | 0.8 km |
| Green Lane, Stewartby - Solar PV Array | Power plant | 30 MW | Planned | 0.8 km |
| Marston Rd Grid 33kV | Substation | — | — | 1.0 km |
| Marston Rd Primary 11kV | Substation | — | — | 1.2 km |
| West Bedford Primary 11kV | Substation | — | — | 4.3 km |
| Pulsant Milton Keynes SE-1 | Data center | — | — | 16 km |
| Data center, England (OSM way 460010263) | Data center | — | — | 16 km |
| Data center, Dunstable (OSM way 526426719) | Data center | — | — | 19 km |
Holder, grid operator and place
More from Infinis Limited
- (ANM) Sandy Lane grid connection15 MW
- Sutton Courtenay Landfill Site grid connection14.3 MW
- Sutton Courtenay grid connection12.5 MW
- Brogborough Power Station T1, T2, T3, T4 grid connection10.5 MW
- Gowy Landfill 5 grid connection8 MW
- (ANM) Dogsthorpe Landfill Site grid connection7 MW
- Greenway Waste Management - Hanson Aveley Landfill Site grid connection6 MW
- Waste 2.375 MW grid connection at CALNE2.38 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.