Grid connection · England, United Kingdom

Battery storage and Solar 51.87 MW grid connection at Stripe Lane Hybrid

Battery storage and Solar 51.87 MW grid connection at Stripe Lane Hybrid is a planned grid connection in England, United Kingdom, with 51.9 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Stripe Lane Hybrid)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toPoppleton (via a bulk supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity51.9 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date16 Dec 2024Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage33 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.9969, -1.1555Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Battery storage and Solar 51.87 MW grid connection at Stripe Lane Hybrid is the 531st-largest of 2,533 grid connections in England and the 778th-largest of 3,903 in the United Kingdom by capacity; its 51.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England531st of 2,533319,370 MW<0.1%
United Kingdom778th of 3,903446,745 MW<0.1%
All grid connections in our data4,021st of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 299 power plants (77 operating, 3,639 MW), 222 substations, 4 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Overton Grange, Overton Road - Solar Farm Battery Energy StoragePower plant49.9 MWPlanned0.7 km
Poppleton Solar FarmPower plant32.6 MWPermitted1.5 km
PoppletonSubstation——2.9 km
Moor Monkton PumpsSubstation——3.2 km
Hessay Solar FarmPower plant40 MWPermitted3.6 km
Rawcliffe LaneSubstation——3.7 km
Yorkshire GREENTransmission line—Permitted13 km
VocaLinkData center——27 km
HSBC Wakefield Data CentreData center——36 km

Grid operator and place

More from Northern Powergrid (Northeast) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page