Battery storage 50 MW grid connection at TeesCAES Storage Direct
Battery storage 50 MW grid connection at TeesCAES Storage Direct is a planned grid connection in England, United Kingdom, with 50 MW of capacity, connected by Northern Powergrid (Northeast) plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connection site: TeesCAES Storage Direct) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Status | Planned (Accepted To Connect) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Capacity | 50 MW | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Grid operator | Northern Powergrid (Northeast) plc | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Queue date | 30 Jan 2026 | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Coordinates | 54.5997, -1.1943 | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its grid operator? Ask us.
How it compares
Battery storage 50 MW grid connection at TeesCAES Storage Direct is the 538th-largest of 2,533 grid connections in England and the 804th-largest of 3,903 in the United Kingdom by capacity; its 50 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 538th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 804th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 3,801st of 7,616 | 1,281,251 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 253 power plants (80 operating, 720 MW) and 141 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Tees Valley Renewable Energy Facility - TV2 | Power plant | 49 MW | Cancelled | 0.1 km |
| Lighthouse Green Fuels Project (WITHDRAWN) | Power plant | 150 MW | Cancelled | 0.3 km |
| Seal Sands | Substation | — | — | 0.9 km |
| Lighthouse Green Fuels Project | Power plant | 200 MW | Planned | 1.2 km |
| Tees Industrial T1 T2 | Substation | — | — | 1.7 km |
| Saltholme | Substation | — | — | 2.9 km |
Grid operator and place
More from Northern Powergrid (Northeast) plc
- Biomass 399 MW grid connection at Lynemouth Power Direct399 MW
- Battery storage and Solar 320.3 MW grid connection at Colliery Farm SPV & BESS Direct320 MW
- Battery storage 250 MW grid connection at Old Hill Farm Direct250 MW
- Battery storage and Solar 200 MW grid connection at Clock and Grimeston Farm Direct200 MW
- Solar 200 MW grid connection at Scampston Solar Direct200 MW
- Solar 180 MW grid connection at Mill Lane Direct180 MW
- Mill Lane Solar PV grid connection180 MW
- Battery storage 175 MW grid connection at West Boldon Farm BESS Direct175 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- CAISO queue report. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, No restriction on the posted data.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, No restriction on the posted data.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.