Grid connection · England, United Kingdom

Battery storage 49.9 MW grid connection at Greenfield Produce BESS Direct

Battery storage 49.9 MW grid connection at Greenfield Produce BESS Direct is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Greenfield Produce BESS Direct)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toWestfield Road, Carlton - Battery Storage (matched by coordinates+technology+capacity, 0.29 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toSkelton Grange (via a grid supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity49.9 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date17 May 2022Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage132 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7385, -1.4894Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Battery storage 49.9 MW grid connection at Greenfield Produce BESS Direct is the 597th-largest of 2,533 grid connections in England and the 904th-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England597th of 2,533319,370 MW<0.1%
United Kingdom904th of 3,903446,745 MW<0.1%
All grid connections in our data3,992nd of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 400 power plants (107 operating, 4,022 MW), 368 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Westfield Road, Carlton - Battery StoragePower plant50 MWPermitted0.3 km
Royds LaneSubstation——1.3 km
OutwoodSubstation——2.7 km
Stourton 132/11kV DirectSubstation——3.0 km
Headways, Unit 3 - Solar PanelsPower plant1 MWPermitted3.4 km
Phoenix Healthcare Distribution Centre - Battery StoragePower plant3.4 MWPermitted3.9 km
Yorkshire GREENTransmission line—Permitted23 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page