Grid connection · England, United Kingdom
Battery storage 30 MW grid connection at West Sleekburn BESS
Battery storage 30 MW grid connection at West Sleekburn BESS is a planned grid connection in England, United Kingdom, with 30 MW of capacity, connected by Northern Powergrid (Northeast) plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connection site: West Sleekburn BESS) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Status | Planned (Accepted To Connect) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Attached to | West Sleekburn - Battery Storage Compound (method: coordinates+technology+capacity, distance km: 0.1) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Capacity | 30 MW | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Technology | Battery storage | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Grid operator | Northern Powergrid (Northeast) plc | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Queue date | 7 Jul 2022 | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Voltage | 66 kV | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Coordinates | 55.1595, -1.5417 | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its grid operator? Ask us.
How it compares
Battery storage 30 MW grid connection at West Sleekburn BESS is the 857th-largest of 2,533 grid connections in England and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 857th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,333rd of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,564th of 7,616 | 1,281,251 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 183 power plants (65 operating, 1,063 MW) and 111 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| West Sleekburn - Battery Storage Compound | Power plant | 30 MW | Permitted | 0.1 km |
| Wansbeck | Substation | — | — | 0.4 km |
| High Brockland Farm, Brock Lane - Battery Energy Storage System | Power plant | 70 MW | Permitted | 0.5 km |
| Blyth 132kV | Substation | — | — | 2.2 km |
| Blyth 66kV | Substation | — | — | 2.2 km |
| Land East of Mount Pleasant Farm | Power plant | 1.5 MW | Cancelled | 2.4 km |
Grid operator and place
More from Northern Powergrid (Northeast) plc
- Biomass 399 MW grid connection at Lynemouth Power Direct399 MW
- Battery storage and Solar 320.3 MW grid connection at Colliery Farm SPV & BESS Direct320 MW
- Battery storage 250 MW grid connection at Old Hill Farm Direct250 MW
- Battery storage and Solar 200 MW grid connection at Clock and Grimeston Farm Direct200 MW
- Solar 200 MW grid connection at Scampston Solar Direct200 MW
- Solar 180 MW grid connection at Mill Lane Direct180 MW
- Mill Lane Solar PV grid connection180 MW
- Battery storage 175 MW grid connection at West Boldon Farm BESS Direct175 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- CAISO queue report. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, No restriction on the posted data.
- PJM New Services Queue. PJM New Services Queue, No restriction on the posted data.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.