Grid connection · Scotland, United Kingdom

Standingfauld Farm - Solar grid connection

Standingfauld Farm - Solar grid connection is a planned grid connection in Scotland, United Kingdom, with 9.9 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSTANDINGFAULD FARM - SOLAR grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Braco West Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toBraco West GSP (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity9.9 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date16 Jul 2024SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Aug 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates56.3004, -3.8371SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Standingfauld Farm - Solar grid connection is the 690th-largest of 1,192 grid connections in Scotland and the 2,154th-largest of 3,903 in the United Kingdom by capacity; its 9.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland690th of 1,19288,894 MW<0.1%
United Kingdom2,154th of 3,903446,745 MW<0.1%
All grid connections in our data5,756th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 294 power plants (83 operating, 1,046 MW) and 47 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Standingfauld FarmPower plant20 MWCancelled0.5 km
Standingfauld Farm, Muthill - Solar PanelsPower plant14 MWPermitted0.8 km
Strathallan Wind FarmPower plant20.7 MWUnder construction5.2 km
Gleneagles PrimarySubstation——5.5 km
Braco West GSPSubstation——8.0 km
Crieff PrimarySubstation——8.6 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom