Grid connection · Scotland, United Kingdom

Shelloch B Wind Farm grid connection

Shelloch B Wind Farm grid connection is a planned grid connection in Scotland, United Kingdom, with 25 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSHELLOCH B WIND FARM grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connection site: STRATHLEVEN)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toStrathleven GSP (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity25 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date16 Aug 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates56.1021, -4.1812SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Shelloch B Wind Farm grid connection is the 615th-largest of 1,518 grid connections in Scotland and the 1,653rd-largest of 4,493 in the United Kingdom by capacity; its 25 MW is <0.1% of the 459,551 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland615th of 1,51896,638 MW<0.1%
United Kingdom1,653rd of 4,493459,551 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 32 substations, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Kippen PrimarySubstation——4.1 km
Kepculloch PrimarySubstation——11 km
Aberfoyle PrimarySubstation——14 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1518 grid connections in Scotland, United Kingdom