Grid connection · Scotland, United Kingdom

Rothie 3 BESS grid connection

Rothie 3 BESS grid connection is a planned grid connection in Scotland, United Kingdom, with 75 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceROTHIE 3 BESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Rothienorman)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toRothienorman GSP (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity75 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date8 Sept 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Jun 2030 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.4103, -2.4977SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Rothie 3 BESS grid connection is the 92nd-largest of 1,192 grid connections in Scotland and the 568th-largest of 3,903 in the United Kingdom by capacity; its 75 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland92nd of 1,19288,894 MW<0.1%
United Kingdom568th of 3,903446,745 MW<0.1%
All grid connections in our data3,617th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 241 power plants (71 operating, 782 MW), 88 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Rothienorman GSPSubstation——1.1 km
Hill Of RothmaisePower plant4.6 MWCancelled1.3 km
Middleton Of Blackhills, Rothienorman - Battery Energy Storage SystemPower plant49.9 MWPlanned1.4 km
Overhill Farm, Rothienorman - Battery Energy StoragePower plant49.9 MWUnder construction1.4 km
Fyvie PrimarySubstation——6.8 km
Insch PrimarySubstation——10.0 km
BrightsolidData center——35 km