Grid connection · Scotland, United Kingdom

North HOO Field Ltd grid connection

North HOO Field Ltd grid connection is a planned grid connection in Scotland, United Kingdom, with 2.3 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceNORTH HOO FIELD LTD grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Gremista 11KV Switchroom)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity2.3 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date14 Apr 2025SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date14 Apr 2026 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates60.1686, -1.1684SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

North HOO Field Ltd grid connection is the 988th-largest of 1,192 grid connections in Scotland and the 3,243rd-largest of 3,903 in the United Kingdom by capacity; its 2.3 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland988th of 1,19288,894 MW<0.1%
United Kingdom3,243rd of 3,903446,745 MW<0.1%
All grid connections in our data6,935th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 16 power plants (5 operating, 452 MW) and 10 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Shetland / GremistaSubstation——0.3 km
Shetland Battery Energy Storage SystemPower plant70 MWUnder construction0.4 km
Lerwick PrimarySubstation——0.4 km
Northern Isles New Energy Solution (NINES) 1Power plant1 MWOperating0.4 km
North Hoo FieldsPower plant2.3 MWPermitted0.6 km
Scalloway PrimarySubstation——5.9 km