Grid connection · Scotland, United Kingdom
Frodo & Bilbo Farm Solar/BESS grid connection
Frodo & Bilbo Farm Solar/BESS grid connection is a planned grid connection in Scotland, United Kingdom, with 74.6 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | FRODO & BILBO FARM SOLAR/BESS grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | Scotland (connects at Strichen Grid) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Frodo Solar and Battery Energy Development (matched by shared name+coordinates+technology+capacity, 1.61 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | Strichen Primary (via a primary substation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 74.6 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Scottish Hydro Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 4 Nov 2022 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 31 Aug 2026 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 57.6005, -1.8852 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.
Request researchHow it compares
Frodo & Bilbo Farm Solar/BESS grid connection is the 97th-largest of 1,192 grid connections in Scotland and the 581st-largest of 3,903 in the United Kingdom by capacity; its 74.6 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 97th of 1,192 | 88,894 MW | <0.1% |
| United Kingdom | 581st of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 3,655th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Was due to connect; the register does not list it as connected
Nearby
Within 50 km of this grid connection: 150 power plants (50 operating, 297 MW) and 38 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Bilbo Solar Farm Energy Storage | Power plant | 40 MW | Under construction | 1.2 km |
| Greenside Extension - Wind Turbines | Power plant | 7.05 MW | Permitted | 1.4 km |
| Frodo Solar and Battery Energy Development | Power plant | 60.1 MW | Permitted | 1.6 km |
| St Fergus GSP | Substation | — | — | 3.4 km |
| Mintlaw Primary | Substation | — | — | 10 km |
| Strichen GSP | Substation | — | — | 11 km |
Grid operator and place
More from Scottish Hydro Electric Power Distribution plc
- 60MW PV/Wind/BESS grid connection180 MW
- Wester Covesea Solar, Wind and Storage grid connection180 MW
- Sloy Power Station grid connection160 MW
- Seggiecrook Farm BESS and Solar grid connection126 MW
- Ledyatt Farm grid connection124 MW
- Balgonie Farm grid connection120 MW
- Fragland grid connection120 MW
- Jamesfield Farm grid connection120 MW
Other grid connections in Scotland
- Marram Wind Offshore Wind Farm grid connection3,000 MW
- OWPL Windfarm grid connection2,250 MW
- Caledonia Offshore Wind Farm grid connection2,000 MW
- Machair Offshore Wind Farm grid connection2,000 MW
- Arven Offshore Wind Farm grid connection1,800 MW
- Bellrock Offshore Wind Farm grid connection1,800 MW
- Earba PSH grid connection1,800 MW
- Glen Earrach PSH grid connection1,800 MW
Data on this page
- California ISO. The terms cover every document on caiso.com, the cluster reports included. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.