Grid connection · England, United Kingdom

Waste 1.31 MW grid connection at Ashington

Waste 1.31 MW grid connection at Ashington is a grid connection in England, United Kingdom, with 1.31 MW of capacity, connected by Northern Powergrid (Northeast) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Ashington)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (connected)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toAshington (via a primary substation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity1.31 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWasteNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Northeast) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date18 May 2015Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Connection date30 Dec 1999Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates55.1729, -1.5663Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Waste 1.31 MW grid connection at Ashington is the 2,371st-largest of 2,533 grid connections in England and the 3,670th-largest of 3,903 in the United Kingdom by capacity; its 1.31 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,371st of 2,533319,370 MW<0.1%
United Kingdom3,670th of 3,903446,745 MW<0.1%
All grid connections in our data7,374th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Connected
  2. Entered the connection queue

Nearby

Within 50 km of this grid connection: 178 power plants (62 operating, 1,048 MW) and 111 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
AshingtonSubstation——0.2 km
High Brockland Farm, Brock Lane - Battery Energy Storage SystemPower plant70 MWPermitted2.1 km
WansbeckSubstation——2.3 km
West Sleekburn - Battery Storage CompoundPower plant30 MWPermitted2.3 km
New Moor ShaftPower plant4.2 MWCancelled3.3 km
LynemouthSubstation——4.1 km

Grid operator and place

More from Northern Powergrid (Northeast) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom