Grid connection · England, United Kingdom
Tillingham Power grid connection
Tillingham Power grid connection is a grid connection in England, United Kingdom, with 15.2 MW of capacity, connected by Southern Electric Power Distribution plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | TILLINGHAM POWER grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Victor Way Generation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating (connected) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Pyestock BSP (via a bulk supply point) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 15.2 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Gas | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Southern Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 29 Oct 2016 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 51.2794, -0.8018 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.
Request researchHow it compares
Tillingham Power grid connection is the 1,185th-largest of 2,533 grid connections in England and the 1,876th-largest of 3,903 in the United Kingdom by capacity; its 15.2 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,185th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,876th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 5,687th of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 248 power plants (92 operating, 778 MW), 236 substations, 107 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Data center, England (OSM way 1164817477) | Data center | — | — | 0.3 km |
| Ark Data Centres data center, England | Data center | — | — | 0.4 km |
| Datum Farnborough Data Centre | Data center | — | — | 0.4 km |
| Pyestock BSP | Substation | — | — | 0.9 km |
| Pyestock Primary | Substation | — | — | 0.9 km |
| Farnborough Airport - Solar Panels | Power plant | 1.7 MW | Operating | 2.0 km |
| Crookham Primary | Substation | — | — | 2.1 km |
| Farnborough International Exhibition Centre, Etps Road - Solar Panels | Power plant | 1.15 MW | Under construction | 3.2 km |
| Coxmoor Wood, Crondall Road - Battery Storage | Power plant | 57 MW | Permitted | 4.7 km |
Grid operator and place
More from Southern Electric Power Distribution plc
- Weston Lane (G) grid connection450 MW
- 200MW BESS grid connection200 MW
- 200MW BESS grid connection200 MW
- Ready - 200MW Battery grid connection200 MW
- Witney Bypass - 150MW BESS grid connection160 MW
- Norrington Gate Battery 150MW grid connection150 MW
- Stonehill grid connection150 MW
- Fawley North Cogeneration Connection grid connection138 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. The terms cover every document on caiso.com, the cluster reports included. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.