Grid connection · England, United Kingdom

Witney Bypass - 150MW BESS grid connection

Witney Bypass - 150MW BESS grid connection is a planned grid connection in England, United Kingdom, with 160 MW of capacity, connected by Southern Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceWITNEY BYPASS - 150MW BESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Witney)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toWitney Bypass, Stanton Harcourt Road - Battery Storage (matched by shared name+coordinates+technology+capacity, 0.21 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toWitney BSP (via a bulk supply point)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity160 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date30 Aug 2024SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Nov 2038 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.7675, -1.4830SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit applied for: Witney Bypass, Stanton Harcourt Road - Battery Storage (planning authority West Oxfordshire, reference 25/01656/FUL)

How it compares

Witney Bypass - 150MW BESS grid connection is the 256th-largest of 2,533 grid connections in England and the 341st-largest of 3,903 in the United Kingdom by capacity; its 160 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England256th of 2,533319,370 MW<0.1%
United Kingdom341st of 3,903446,745 MW<0.1%
All grid connections in our data2,339th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 309 power plants (122 operating, 1,977 MW), 128 substations and 10 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Witney Bypass, Stanton Harcourt Road - Battery StoragePower plant150 MWPlanned0.2 km
Witney BSPSubstation——0.5 km
Ducklington Solar FarmPower plant36 MWUnder construction1.3 km
Witney Town PrimarySubstation——1.8 km
Windrush Park PrimarySubstation——3.1 km
Tar Solar FarmPower plant40 MWPermitted3.3 km
University Shared Data CentreData center——16 km
AWS Didcot Data CentreData center——23 km
R89Data center——24 km

Grid operator and place

More from Southern Electric Power Distribution plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom