Grid connection · England, United Kingdom

Raikes Lane Incinerator grid connection

Raikes Lane Incinerator grid connection is a grid connection in England, United Kingdom, with 11.7 MW of capacity, held by Viridor Waste Management Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceRAIKES LANE INCINERATOR grid connectionSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Bolton Waste)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusOperating (connected)SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderViridor Waste Management LimitedSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toBolton TRF (matched by coordinates+technology+capacity+company, 0.04 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity11.7 MWSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWasteSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorElectricity North West LimitedSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date1 Jun 2001SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates53.5675, -2.4047SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Commissioned: Bolton TRF
  2. Permit granted: Bolton TRF (planning authority Bolton)
  3. Permit applied for: Bolton TRF (planning authority Bolton)

How it compares

Raikes Lane Incinerator grid connection is the 1,298th-largest of 2,533 grid connections in England and the 2,053rd-largest of 3,903 in the United Kingdom by capacity; its 11.7 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,298th of 2,533319,370 MW<0.1%
United Kingdom2,053rd of 3,903446,745 MW<0.1%
All grid connections in our data5,898th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 418 substations, 406 power plants (116 operating, 1,225 MW), 20 data centers, 3 gas storage facilities and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Bolton TRFPower plant10.8 MWOperating0.0 km
Edbro, Lever Street - Solar PanelsPower plant1.7 MWPermitted1.4 km
Campbell StSubstation——1.4 km
BradshawgateSubstation——1.6 km
Salford RoadPower plant1.6 MWOperating2.0 km
SpA RDSubstation——2.4 km
Evolution @ Agecroft Commerce ParkData center——9.4 km
Data center, England (OSM way 1535147042)Data center——13 km
Joule HouseData center——13 km

Holder, grid operator and place

More from Viridor Waste Management Limited

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page