Grid connection · England, United Kingdom
Generation 100 MW grid connection at Bramley (Flee)
Generation 100 MW grid connection at Bramley (Flee) is a planned grid connection in England, United Kingdom, with 100 MW of capacity, connected by Southern Electric Power Distribution plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | Generation 100 MW grid connection at BRAMLEY (FLEE) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Bramley (Flee)) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 100 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Southern Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 31 Oct 2023 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 31 Oct 2037 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 51.2483, -0.8620 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Know more about this grid connection, or want an introduction to its grid operator? Ask us.
How it compares
Generation 100 MW grid connection at Bramley (Flee) is the 311th-largest of 2,533 grid connections in England and the 412th-largest of 3,903 in the United Kingdom by capacity; its 100 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 311th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 412th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 2,861st of 7,616 | 1,281,251 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 274 power plants (106 operating, 886 MW), 251 substations, 96 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Crondall Road, Crondall - Fleet Bramley Battery Energy Storage | Power plant | 99.9 MW | Permitted | 0.2 km |
| Bowenhurst Farm, Mill Lane - Battery Energy Storage | Power plant | 100 MW | Cancelled | 0.6 km |
| Blue Bell Lodge, Rye Common Lane - Battery Storage | Power plant | 49.5 MW | Permitted | 0.7 km |
| Coxmoor Wood BSP | Substation | — | — | 1.2 km |
| Coxmoor Wood Primary | Substation | — | — | 1.3 km |
| Fleet-Bramley GSP | Substation | — | — | 1.4 km |
| Data center, England (OSM way 1164817477) | Data center | — | — | 5.7 km |
| Datum Farnborough Data Centre | Data center | — | — | 5.8 km |
| Ark Data Centres data center, England | Data center | — | — | 5.8 km |
Grid operator and place
More from Southern Electric Power Distribution plc
- Weston Lane (G) grid connection450 MW
- 200MW BESS grid connection200 MW
- 200MW BESS grid connection200 MW
- Ready - 200MW Battery grid connection200 MW
- Witney Bypass - 150MW BESS grid connection160 MW
- Norrington Gate Battery 150MW grid connection150 MW
- Stonehill grid connection150 MW
- Fawley North Cogeneration Connection grid connection138 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. Checked 2026-10-24. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.