FactValueSource
Name in the sourceBOURNEMOUTH AIRPORT SOLAR PV PLANT grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Redhill)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toRedhill Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity4.1 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date6 May 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date19 Sept 2025 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates50.7776, -1.8323SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Bournemouth Airport Solar PV Plant grid connection is the 1,816th-largest of 2,533 grid connections in England and the 2,823rd-largest of 3,903 in the United Kingdom by capacity; its 4.1 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,816th of 2,533319,370 MW<0.1%
United Kingdom2,823rd of 3,903446,745 MW<0.1%
All grid connections in our data6,803rd of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Nearby

Within 50 km of this grid connection: 248 power plants (112 operating, 952 MW), 157 substations and 7 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Curtiss Wright Controls, Enterprise Way - Solar PanelsPower plant1 MWPermitted1.5 km
Eco CompostingPower plant3.2 MWOperating1.8 km
Parley Renewable Energy Park (AD)Power plant1 MWCancelled1.8 km
Redhill BSPSubstation——3.6 km
Redhill PrimarySubstation——3.7 km
Winton PrimarySubstation——4.5 km
Data Vault - Bournemouth BCP01Data center——6.9 km
Sky ChilworthData center——35 km
SCCData center——42 km