Grid connection · England, United Kingdom

Battery storage 49.9 MW grid connection at Leeds South BESS

Battery storage 49.9 MW grid connection at Leeds South BESS is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Leeds South BESS)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toBuslingthorpe Green - Battery Energy Storage (matched by coordinates+technology+capacity, 0.14 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toLeeds North (via a bulk supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity49.9 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date11 Aug 2022Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage33 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.8167, -1.5422Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit granted: Buslingthorpe Green - Battery Energy Storage (planning authority Leeds, reference 24/02389/FU)
  2. Permit applied for: Buslingthorpe Green - Battery Energy Storage (planning authority Leeds, reference 24/02389/FU)

How it compares

Battery storage 49.9 MW grid connection at Leeds South BESS is the 597th-largest of 2,533 grid connections in England and the 904th-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England597th of 2,533319,370 MW<0.1%
United Kingdom904th of 3,903446,745 MW<0.1%
All grid connections in our data4,270th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 391 substations, 381 power plants (103 operating, 3,904 MW), 11 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Buslingthorpe Green - Battery Energy StoragePower plant49.9 MWPermitted0.1 km
Buslingthorpe Power Station (Leeds North)Power plant2 MWOperating0.2 km
Leeds NorthSubstation——0.3 km
Buslingthorpe GreenSubstation——0.3 km
Carlton HillSubstation——1.2 km
Redcote Lane, Armley - Battery Storage FacilityPower plant60 MWPermitted3.1 km
GridJetData center——4.3 km
nLighten LeedsData center——16 km
HSBC Wakefield Data CentreData center——17 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page