(ANM) SS17 9LL The Manorway grid connection is a planned grid connection in England, United Kingdom, with 20 MW of capacity, connected by Eastern Power Networks plc (UK Power Networks, East England licence area).

Map: where (ANM) SS17 9LL The Manorway grid connection lies
51.5130, 0.5124 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Coryton Grid 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity20 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyGasUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date28 Sept 2021UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date30 Nov 2024 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.5130, 0.5124UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

(ANM) SS17 9LL The Manorway grid connection is the 1,321st-largest of 3,539 grid connections in England and the 1,923rd-largest of 4,870 in the United Kingdom by capacity; its 20 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,321st of 3,539341,715 MW<0.1%
United Kingdom1,923rd of 4,870467,981 MW<0.1%
All grid connections in our data5,304th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Nearby

Within 50 km of this grid connection: 395 substations, 359 power plants (147 operating, 8,373 MW), 55 data centers (1 operating, 88 MW), 1 AI supercomputer and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Coryton Energy Company LtdPower plant800 MWOperating0.3 km
Coryton Grid 33kVSubstation——0.8 km
Gateway Energy Centre - Battery Energy StoragePower plant450 MWPermitted1.0 km
Land adjacent to the former Coryton RefineryPower plant5 MWCancelled1.2 km
Shell Grid 33kVSubstation——4.0 km
Canvey Primary 11kVSubstation——4.5 km
Imperium 315Data center——8.4 km
CityFibre CabinetsData center——11 km
Fujitsu Data CentreData center——17 km

Grid operator and place

More from Eastern Power Networks plc

Other grid connections in England

All 4837 grid connections in England, United Kingdom