Power plant · Vale of Glamorgan, Wales, United Kingdom

Treguff Farm

Treguff Farm is a power plant in Vale of Glamorgan, Wales, United Kingdom, with 4.4 MW of capacity, operated by Lightsource Renewable Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationVale of Glamorgan (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressTreguff Farm, St. Mary Church, Cowbridge, CF71 7LTDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2015DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date12 Aug 2014 (permit 2013/00912/FUL, Town and Country Planning Act, issued by Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date24 Sept 2013 (reference 2013/00912/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date17 Jan 2014 (refused, reference 2013/00912/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Aug 2014 (granted, reference 2013/00912/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 Aug 2014 (appeal granted, reference 2013/00912/FUL, planning authority Vale of Glamorgan)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLightsource Renewable EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity4.4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area10.8 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4312, -3.4048DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Vale of Glamorgan, reference 2013/00912/FUL)
  3. Permit granted (appeal granted, planning authority Vale of Glamorgan, reference 2013/00912/FUL)
  4. Permit refused (planning authority Vale of Glamorgan, reference 2013/00912/FUL)
  5. Permit applied for (planning authority Vale of Glamorgan, reference 2013/00912/FUL)

How it compares

Treguff Farm is the 292nd-largest of 424 power plants in Wales and the 3,439th-largest of 5,050 in the United Kingdom by capacity; its 4.4 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales292nd of 4249,068 MW<0.1%
United Kingdom3,439th of 5,050115,622 MW<0.1%
All power plants in our data9,175th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 8 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 5, up to 3 per kind.

NameKindSizeStatusDistance
CGI DatacenterData center——14 km
Centerprise International (Distribution)Data center——25 km
Microsoft Newport data centreData center——29 km
Hinkley Point C Connection Project Material ChangeTransmission line—Planned41 km
Hinkley Point C ConnectionTransmission line—Permitted45 km