Power plant · Renfrewshire, Scotland, United Kingdom

Middleton Road - Linwood Battery Energy Storage System

Middleton Road - Linwood Battery Energy Storage System is a cancelled battery storage plant in Renfrewshire, Scotland, United Kingdom, with 69 MW of capacity, operated by Bluestone Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRenfrewshire (coordinates), ScotlandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressMiddleton Road, Linwood, Paisley, PA3 3DPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (abandoned)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date16 May 2024 (permit ECU00004543, Electricity Act 1989 section 36, issued by Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date20 Feb 2023 (reference ECU00004543, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date16 May 2024 (granted, reference ECU00004543, planning authority Scottish Government (S36))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBluestone Energy (applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity69 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates55.8544, -4.4851DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Scottish Government (S36), reference ECU00004543)
  2. Permit applied for (planning authority Scottish Government (S36), reference ECU00004543)

How it compares

Middleton Road - Linwood Battery Energy Storage System is the 106th-largest of 1,340 power plants in Scotland and the 348th-largest of 5,834 in the United Kingdom by capacity; its 69 MW is <0.1% of the 200,500 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Scotland106th of 1,34046,467 MW0.15%
United Kingdom348th of 5,834200,500 MW<0.1%
All power plants in our data3,052nd of 15,7991,918,113 MW<0.1%

Nearby

Within 50 km of this power plant: 22 substations, 16 grid connections (9 operating, 223 MW) and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
iomart Glasgow Data CentreData center——13 km
Strathleven GSPSubstation——13 km
Verizon Glasgow GLSGGBData center——13 km
DataVita DV2Data center——14 km
Auchencarroch Energy Ltd grid connectionGrid connection3.04 MWOperating16 km
Auchincarroch (GEN464G2) grid connectionGrid connection1.01 MWOperating16 km
Blairlinnans PrimarySubstation——20 km
Dumfin 11kV NetworkSubstation——22 km
Ross Priory Hydro grid connectionGrid connection4 MWPlanned22 km