Power plant · North Lincolnshire, England, United Kingdom

Winterton Road - Battery Energy Storage

Winterton Road - Battery Energy Storage is a permitted power plant in North Lincolnshire, England, United Kingdom, with 95 MW of capacity, operated by Newton Energi Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Lincolnshire (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressN/O Gala Bingo, Winterton Road, Scunthorpe, DN15 0DHDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date16 Dec 2022 (permit PA/2021/1291, Town and Country Planning Act, issued by North Lincolnshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date12 Aug 2021 (ref. PA/2021/1291, North Lincolnshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date16 Dec 2022 (granted, ref. PA/2021/1291, North Lincolnshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNewton Energi LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity95 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBatteryDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.5980, -0.6380DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Winterton Road - Battery Energy Storage is the 334th-largest of 2,174 power plants planned, permitted or under construction in England and the 545th-largest of 3,222 in the United Kingdom by capacity; its 95 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England334th of 2,174186,088 MW<0.1%
United Kingdom545th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,460th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 424 grid connections (182 operating, 2,590 MW), 178 substations, 2 transmission lines and 1 CO2 emitter, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Battery storage 80 MW grid connection at Vox Winterton BESS DirectGrid connection80 MWPlanned0.2 km
Solar 20 MW grid connection at Winterton Road PVGrid connection20 MWPlanned0.8 km
Station RoadSubstation——1.0 km
Scunthorpe NorthSubstation——1.0 km
Gas 20 MW grid connection at Marden PowerGrid connection20 MWOperating1.1 km
Firth BrownSubstation——1.5 km
North Humber to High MarnhamTransmission line—Planned22 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled27 km
Aldbrough Hydrogen StorageCO2 emitter—Planned43 km

Operator and place

Grid connections attached to this power plant

More from Newton Energi Limited

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page