Power plant · West Suffolk, England, United Kingdom

Honington Solar Farm

Honington Solar Farm is a power plant in West Suffolk, England, United Kingdom, with 13.6 MW of capacity, operated by NextEnergy Solar Fund.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWest Suffolk (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand at Euston Estate, Honnington, SuffolkDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Dec 2012 (permit SE/12/1069/FUL, Town and Country Planning Act, issued by West Suffolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Aug 2012 (reference SE/12/1069/FUL, planning authority West Suffolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Dec 2012 (granted, reference SE/12/1069/FUL, planning authority West Suffolk)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNextEnergy Solar Fund (NextEnergy Solar Fund (NESF))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity13.6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area22.6 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.3401, 0.7921DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority West Suffolk, reference SE/12/1069/FUL)
  3. Permit applied for (planning authority West Suffolk, reference SE/12/1069/FUL)

How it compares

Honington Solar Farm is the 864th-largest of 3,430 power plants in England and the 1,535th-largest of 5,050 in the United Kingdom by capacity; its 13.6 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England864th of 3,43071,965 MW<0.1%
United Kingdom1,535th of 5,050115,622 MW<0.1%
All power plants in our data5,645th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 3 data centers and 2 transmission lines, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
US Air Force data center, BrandonData center——18 km
Bramford to TwinsteadTransmission line—Permitted37 km
Norwich to TilburyTransmission line—Planned42 km
Redcentric CambridgeData center——45 km
Longmarsh Green EnergyData center—Planned48 km

Operator and place

More from NextEnergy Solar Fund

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page