RARE CONTEXT Request research

Grid connection · England, United Kingdom

Bury Road grid connection

Bury Road grid connection is a grid connection in England, United Kingdom, with 49.9 MW of capacity, held by MJS Grid Services Limited.

Map: where Bury Road grid connection lies
52.3495, 0.7494 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Bramford)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusOperating (connected)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderMJS Grid Services LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity49.9 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date30 Aug 2019UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date12 Sept 2024UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage132 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.3495, 0.7494UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Bury Road grid connection is the 698th-largest of 3,539 grid connections in England and the 997th-largest of 4,870 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England698th of 3,539341,715 MW<0.1%
United Kingdom997th of 4,870467,981 MW<0.1%
All grid connections in our data4,183rd of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 270 power plants (101 operating, 1,661 MW), 130 substations, 4 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Honington Solar FarmPower plant13.6 MWOperating3.1 km
West Farm (Barnham)Power plant29 MWCancelled3.1 km
Ingham North SolarPower plant14.2 MWOperating4.1 km
Honington Primary 11kVSubstation——4.1 km
Thetford Grid 11kVSubstation——4.2 km
Kimms Belt Primary 11kVSubstation——6.3 km
US Air Force data center, BrandonData center——15 km
Bramford to TwinsteadTransmission line—Permitted39 km
Redcentric CambridgeData center——43 km

Holder, grid operator and place

More from MJS Grid Services Limited

Other grid connections in England

All 4837 grid connections in England, United Kingdom

Data on this page