Power plant · Somerset, England, United Kingdom
Bearley Lane
Bearley Lane is a power plant in Somerset, England, United Kingdom, with 1.3 MW of capacity, operated by Greener for Life Energy.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Somerset (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land Os 0002 Bearley Lane, Tintinhull, Yeovil, BA22 8PE | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2021 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 21 Mar 2017 (permit 14/00230/FUL, Town and Country Planning Act, issued by Somerset) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 19 Mar 2014 (reference 14/00230/FUL, planning authority Somerset) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 21 Mar 2017 (granted, reference 14/00230/FUL, planning authority Somerset) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Greener for Life Energy | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 1.3 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Anaerobic Digestion | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 50.9966, -2.7161 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
Bearley Lane is the 3,166th-largest of 3,430 power plants in England and the 4,704th-largest of 5,050 in the United Kingdom by capacity; its 1.3 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 3,166th of 3,430 | 71,985 MW | <0.1% |
| United Kingdom | 4,704th of 5,050 | 115,642 MW | <0.1% |
| All power plants in our data | 11,374th of 12,008 | 1,173,302 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Permit issued (Town and Country Planning Act), no. 14/00230/FUL
- Started operating
Nearby
Within 50 km of this power plant: 270 grid connections (54 operating, 409 MW), 49 substations, 2 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Fleet Air Arm Museum grid connection | Grid connection | 4.01 MW | Operating | 5.1 km |
| Bower Hinton Farm grid connection | Grid connection | — | — | 6.2 km |
| Larkhill Primary | Substation | — | — | 6.5 km |
| Tengore Lane, Langport grid connection | Grid connection | — | — | 7.2 km |
| Chilton Cantello Primary | Substation | — | — | 8.1 km |
| West Hendford Primary | Substation | — | — | 8.5 km |
| Tata Communications Highbridge Datacentre | Data center | — | — | 31 km |
| Hinkley Point C Connection | Transmission line | — | Permitted | 38 km |
| Hinkley Point C Connection Project Material Change | Transmission line | — | Planned | 39 km |
Operator and place
More from Greener for Life Energy
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.