Heaten Hall Farm BESS grid connection is a planned grid connection in England, United Kingdom, with 240 MW of capacity, held by BSR Applications Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | HEATEN HALL FARM BESS grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Royton) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | BSR Applications Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Royton BSP (via a bulk supply point) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 240 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 26 Oct 2023 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 54.0194, -2.8844 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Heaten Hall Farm BESS grid connection is the 226th-largest of 2,533 grid connections in England and the 309th-largest of 3,903 in the United Kingdom by capacity; its 240 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 226th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 309th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 1,552nd of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 190 power plants (71 operating, 3,699 MW), 148 substations, 2 transmission lines and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Trimpell BSP | Substation | — | — | 0.6 km |
| Lancaster Power Extension, Middleton Road - Energy Storage Facility | Power plant | 50 MW | Cancelled | 0.9 km |
| Lancaster West Business Park | Power plant | 30 MW | Cancelled | 1.0 km |
| Heysham GSP | Substation | — | — | 1.6 km |
| Heysham Energy Storage Project | Power plant | 200 MW | Cancelled | 2.0 km |
| Westgate | Substation | — | — | 4.9 km |
| Preesall Saltfield Underground Gas Storage | Gas storage facility | — | Cancelled | 14 km |
| East Irish Sea Transmission Project | Transmission line | — | Planned | 18 km |
| Morgan and Morecambe Offshore Wind Farms Transmission Assets | Transmission line | — | Permitted | 30 km |
Holder, grid operator and place
More from BSR Applications Limited
- Cold Norton grid connection1,250 MW
- Stockhills Farm grid connection800 MW
- Heaten Hall Farm BESS+Wind grid connection240 MW
- Wester Covesea Solar, Wind and Storage grid connection180 MW
- Land at Frog Lane grid connection70 MW
- North Dairy Farm - Solar PV (Flexible Connection) grid connection50 MW
- The Knells Solar grid connection49.9 MW
- Stroud Farm Solar and Storage grid connection36 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.