Grid connection · Scotland, United Kingdom

SP - Nairn BESS 49.9MW Battery grid connection

SP - Nairn BESS 49.9MW Battery grid connection is a planned grid connection in Scotland, United Kingdom, with 49.9 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSP - NAIRN BESS 49.9MW BATTERY grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connection site: NAIRN)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toNairn GSP (via: gsp)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity49.9 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date22 Mar 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

SP - Nairn BESS 49.9MW Battery grid connection is the 261st-largest of 1,192 grid connections in Scotland and the 904th-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland261st of 1,19288,894 MW<0.1%
United Kingdom904th of 3,903446,745 MW<0.1%
All grid connections in our data3,992nd of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page