Grid connection · Scotland, United Kingdom

Bunloinn Wind Farm and BESS grid connection

Bunloinn Wind Farm and BESS grid connection is a planned grid connection in Scotland, United Kingdom, with 71.6 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBUNLOINN WIND FARM AND BESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Fort Augustus)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toFort Augustus GSP (via a grid supply point)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity71.6 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date5 Jun 2025SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2035 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.1708, -4.8479SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Bunloinn Wind Farm and BESS grid connection is the 107th-largest of 1,192 grid connections in Scotland and the 593rd-largest of 3,903 in the United Kingdom by capacity; its 71.6 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland107th of 1,19288,894 MW<0.1%
United Kingdom593rd of 3,903446,745 MW<0.1%
All grid connections in our data3,407th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 115 power plants (52 operating, 1,614 MW) and 38 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Tomchrasky Estate Wind farmPower plant50 MWPermitted1.4 km
Tomchrasky Estate Wind farmPower plant84 MWPermitted1.4 km
Millennium Extension IIPower plant15 MWOperating2.5 km
Ceannacroc GSPSubstation——5.7 km
Fort Augustus GSPSubstation——8.7 km
Bunoich PrimarySubstation——10 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page