Balnacraig Battery Storage grid connection

Balnacraig Battery Storage grid connection is a planned grid connection in Scotland, United Kingdom, with 50 MW of capacity, held by Intelligent Land Investments Group.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBALNACRAIG BATTERY STORAGE grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Alness Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderIntelligent Land Investments GroupSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toAlness GSP (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity50 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date20 Sept 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Jul 2025 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates57.7150, -4.2802SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Balnacraig Battery Storage grid connection is the 220th-largest of 1,192 grid connections in Scotland and the 804th-largest of 3,903 in the United Kingdom by capacity; its 50 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland220th of 1,19288,894 MW<0.1%
United Kingdom804th of 3,903446,745 MW<0.1%
All grid connections in our data3,801st of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 143 power plants (36 operating, 933 MW) and 58 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
The Smithy - Battery StoragePower plant45 MWPermitted0.6 km
Alness GSPSubstation——0.8 km
Contullich PrimarySubstation——1.3 km
Crosshills PrimarySubstation——2.0 km
Strathrory Wind FarmPower plant36 MWPermitted5.9 km
Torr Leathann, Ardross - Battery StoragePower plant5 MWCancelled6.2 km