Grid connection · Scotland, United Kingdom
ABDN Farburn Terrace - Battery grid connection
ABDN Farburn Terrace - Battery grid connection is a planned grid connection in Scotland, United Kingdom, with 30 MW of capacity, held by Balanced Grid Solutions.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | ABDN FARBURN TERRACE - BATTERY grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | Scotland (connects at Dyce) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | Balanced Grid Solutions | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Farburn Place - Battery Energy Storage Facility (matched by shared name+coordinates+technology+capacity, 0.3 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Attached to | Dyce GSP (via a grid supply point) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 30 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Scottish Hydro Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 13 Feb 2020 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 11 Sept 2026 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 57.2027, -2.1921 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchLatest events
Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.
- Permit granted: Farburn Place - Battery Energy Storage Facility (planning authority Aberdeen City, reference 210665/DPP)
- Permit applied for: Farburn Place - Battery Energy Storage Facility (planning authority Aberdeen City, reference 210665/DPP)
How it compares
ABDN Farburn Terrace - Battery grid connection is the 423rd-largest of 1,192 grid connections in Scotland and the 1,333rd-largest of 3,903 in the United Kingdom by capacity; its 30 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| Scotland | 423rd of 1,192 | 88,894 MW | <0.1% |
| United Kingdom | 1,333rd of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,846th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Was due to connect; the register does not list it as connected
Nearby
Within 50 km of this grid connection: 216 power plants (67 operating, 1,838 MW), 77 substations and 1 data center, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Farburn Place - Battery Energy Storage Facility | Power plant | 30 MW | Under construction | 0.3 km |
| Dyce North Primary | Substation | — | — | 0.7 km |
| Dyce GSP | Substation | — | — | 1.5 km |
| Dyce Energy Storage, Raiths Industrial Estate - Battery Facility | Power plant | 50 MW | Operating | 1.5 km |
| Stoneywood (T3) Primary | Substation | — | — | 1.6 km |
| Stoneywood Paper Mill | Power plant | 22 MW | Cancelled | 1.8 km |
| Brightsolid | Data center | — | — | 5.9 km |
Holder, grid operator and place
More from Balanced Grid Solutions
- 49.9MW - Battery grid connection50 MW
- Cowley Battery Storage grid connection50 MW
- 49.9MW Battery grid connection49.9 MW
- Fareham Solar 3 grid connection24 MW
- Botley Energy Reserve 2 grid connection15 MW
- Titchfield Lane49 MW · under construction
- Gaywood Farm7.5 MW
- Hamble Lane Battery Energy Storage6 MW
Other grid connections in Scotland
- Marram Wind Offshore Wind Farm grid connection3,000 MW
- OWPL Windfarm grid connection2,250 MW
- Caledonia Offshore Wind Farm grid connection2,000 MW
- Machair Offshore Wind Farm grid connection2,000 MW
- Arven Offshore Wind Farm grid connection1,800 MW
- Bellrock Offshore Wind Farm grid connection1,800 MW
- Earba PSH grid connection1,800 MW
- Glen Earrach PSH grid connection1,800 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.