57.6MW Wind - Beinn GHLASS grid connection

57.6MW Wind - Beinn GHLASS grid connection is a planned grid connection in Scotland, United Kingdom, with 49.6 MW of capacity, connected by Scottish Hydro Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the source57.6MW WIND - BEINN GHLASS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Taynuilt Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toTaynuilt Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity49.6 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date30 Aug 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2034 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates56.4259, -5.2671SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

57.6MW Wind - Beinn GHLASS grid connection is the 294th-largest of 1,192 grid connections in Scotland and the 1,005th-largest of 3,903 in the United Kingdom by capacity; its 49.6 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland294th of 1,19288,894 MW<0.1%
United Kingdom1,005th of 3,903446,745 MW<0.1%
All grid connections in our data4,101st of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 77 power plants (31 operating, 747 MW) and 54 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Beinn Ghlas Wind Farm - RepoweringPower plant33.6 MWPlanned1.3 km
Cruachan Hydro ExpansionPower plant600 MWPermitted2.3 km
SSE Taynuilt Substation - Battery Energy StoragePower plant49.9 MWPermitted2.6 km
Taynuilt PrimarySubstation——3.2 km
Taynuilt GSPSubstation——3.3 km
Kenmore PrimarySubstation——3.7 km

Grid operator and place

More from Scottish Hydro Electric Power Distribution plc

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom