Grid connection · England, United Kingdom

Waste 5.3 MW grid connection at Stillingfleet

Waste 5.3 MW grid connection at Stillingfleet is a planned grid connection in England, United Kingdom, with 5.3 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Stillingfleet)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toDrax (via a grid supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity5.3 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWasteNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date4 Nov 2019Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage33 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.8615, -1.0894Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Waste 5.3 MW grid connection at Stillingfleet is the 1,648th-largest of 2,533 grid connections in England and the 2,556th-largest of 3,903 in the United Kingdom by capacity; its 5.3 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,648th of 2,533319,370 MW<0.1%
United Kingdom2,556th of 3,903446,745 MW<0.1%
All grid connections in our data6,516th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 380 power plants (95 operating, 3,964 MW), 301 substations, 6 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Broad Lane, Cawood - Solar Farm & Battery StoragePower plant49.9 MWPlanned4.2 km
Broad Lane, Cawood - Solar Farm & Battery StoragePower plant10 MWPlanned4.2 km
Escrick Park Community Power ProjectPower plant4.6 MWCancelled4.5 km
Olympia MillsSubstation——8.8 km
Osgodby 3/4Substation——9.0 km
Campleshon RoadSubstation——9.1 km
Yorkshire GREENTransmission line—Permitted13 km
HSBC Wakefield Data CentreData center——26 km
nLighten LeedsData center——27 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom