Grid connection · England, United Kingdom

The Barn - Solar PV grid connection

The Barn - Solar PV grid connection is a planned grid connection in England, United Kingdom, with 3 MW of capacity, connected by Southern Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceTHE BARN - SOLAR PV grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Minety Village)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toMinety Village Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity3 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date11 Sept 2020SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date26 Jun 2025 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.6296, -1.9780SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

The Barn - Solar PV grid connection is the 1,995th-largest of 2,533 grid connections in England and the 3,064th-largest of 3,903 in the United Kingdom by capacity; its 3 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,995th of 2,533319,370 MW<0.1%
United Kingdom3,064th of 3,903446,745 MW<0.1%
All grid connections in our data7,061st of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Was due to connect; the register does not list it as connected

Nearby

Within 50 km of this grid connection: 390 power plants (145 operating, 1,901 MW), 92 substations, 10 data centers and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Minety Village PrimarySubstation——0.4 km
Cooles Farm, Minety - Solar Park/Battery StoragePower plant8 MWPlanned0.8 km
Land At Moor Lane FarmPower plant4.5 MWCancelled1.2 km
Land at Sandpool FarmPower plant1 MWCancelled2.0 km
Minety GSPSubstation——2.9 km
Kemble RAF PrimarySubstation——6.6 km
Nationwide Swindon Technology CentreData center——12 km
VodafoneData center——13 km
nLighten SwindonData center——17 km

Grid operator and place

More from Southern Electric Power Distribution plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom